Posted on — Leave a comment

The 2026 Nationwide Permits and Florida’s Status Under Nationwide Permit 24

The U.S. Army Corps of Engineers finalized the 2026 Nationwide Permits (NWPs) on January 8, 2026. These permits replace the 2021 Nationwide Permits and will govern a large portion of Clean Water Act Section 404 authorizations nationwide for the next five years. While the overall structure of the nationwide permit program remains largely unchanged, the final rule includes clarifications and targeted revisions that affect how permits are applied, how Clean Water Act Section 401 is implemented, and how state and federal permitting authority is understood.

One of the most discussed changes in the final rule is the removal of Florida from Nationwide Permit 24, which applies in states that have assumed administration of the Section 404 program. Understanding this change requires looking at both how nationwide permits function and how Florida’s assumed program has evolved.

Overview of the Nationwide Permit Program

Nationwide permits are issued by the Corps under Section 404(e) of the Clean Water Act and, where applicable, Section 10 of the Rivers and Harbors Act. They authorize categories of activities that the Corps has determined will result in no more than minimal individual and cumulative adverse environmental effects.

Nationwide permits are designed to streamline permitting for common activities such as utility crossings, bank stabilization, minor road crossings, and maintenance work. They operate subject to:

  • Nationwide permit specific terms and limits
  • Nationwide General Conditions
  • Regional conditions imposed by Corps divisions
  • Clean Water Act Section 401 water quality certification
  • Pre construction notification requirements where applicable

The 2026 Nationwide Permits become effective March 15, 2026 and are scheduled to expire on March 14, 2031.

Key Themes in the 2026 Nationwide Permits

The 2026 NWPs do not represent a major expansion or contraction of the program. Instead, the final rule emphasizes clarity and consistency. Notable themes include:

  • Clarification of how Section 401 water quality certification applies to nationwide permits
  • Greater emphasis on compliance with general conditions
  • Reinforcement of district engineer discretion through regional conditions
  • Clarification of how multiple nationwide permits may be used for a single project

These changes reflect a broader trend toward strengthening the administrative record and reducing ambiguity in permit implementation.


What Nationwide Permit 24 Is

Nationwide Permit 24 is different from most nationwide permits because it applies only in states that have assumed administration of the Clean Water Act Section 404 program under Section 404(g).

When a state assumes the Section 404 program, it becomes the primary permitting authority for most discharges of dredged or fill material into waters of the United States. Federal law, however, does not allow states to assume jurisdiction over all waters. The Corps retains authority over traditionally navigable waters, waters subject to Section 10, and certain adjacent waters.

Nationwide Permit 24 exists to authorize activities in those retained federal waters within assumed states. Its use depends on a clear and legally stable division of permitting authority between the state and the Corps.

Florida’s Section 404 Program Background

Florida began administering a state Section 404 program in December 2020 following approval by the U.S. Environmental Protection Agency. The assumption did not transfer all federal permitting authority to the state. As a result, Florida operated under a divided regulatory framework in which both the state and the Corps issued permits depending on the type and location of waters affected.

Following EPA’s approval, litigation challenged whether the approval complied with the Endangered Species Act, particularly with respect to program level consultation. Federal courts vacated portions of the approval, creating uncertainty regarding the legal foundation of the assumed program.

Removal of Florida From Nationwide Permit 24

In the 2025 proposed Nationwide Permits, Florida continued to be listed as an assumed state under Nationwide Permit 24. The proposal did not suggest removing Florida or solicit comment on that issue.

In the 2026 final rule, the Corps removed Florida from Nationwide Permit 24. The Corps described this change as administrative and stated that it does not affect the number of activities authorized by nationwide permits. The removal aligns the nationwide permits with the current legal status of Florida’s Section 404 program at the time of finalization.

The change becomes effective March 15, 2026, when the 2026 Nationwide Permits take effect.

Practical Implications for Permitting in Florida

With Florida no longer listed under Nationwide Permit 24, the Corps remains the primary federal permitting authority for Section 404 activities involving waters of the United States in Florida, subject to the limits of federal jurisdiction.

Projects in Florida may still rely on other applicable nationwide permits or individual permits issued by the Corps, provided all applicable requirements are met. Clean Water Act Section 401 water quality certification remains required before a nationwide permit authorization becomes valid.

From a practical standpoint, the change underscores the importance of:

  • Verifying permitting authority early in project planning
  • Confirming which nationwide permits apply
  • Tracking state Section 401 certification decisions and conditions
  • Accounting for regional conditions imposed by the Corps

Broader Context

The Florida Nationwide Permit 24 issue highlights how nationwide permits depend on program level legal stability. Nationwide permits are intended to operate consistently across Corps districts. When the status of a state assumed program is uncertain, applying a permit designed specifically for assumed states becomes more complex.

The final rule does not resolve broader questions about the future of Florida’s assumed Section 404 program. Those issues remain subject to future administrative actions and court decisions.

Looking Ahead

The 2026 Nationwide Permits will guide federal wetland permitting through 2031. While many aspects of the program remain familiar, understanding targeted changes and state specific issues such as Florida’s status under Nationwide Permit 24 is essential for effective compliance and project planning.

The Swamp School will be addressing these topics in upcoming training, including a Nationwide Permits webinar on February 19, 2026, which will provide a detailed review of the final permits and their practical implications.

Posted on — Leave a comment

USACOE suspending the existing general permits

Swamp Stomp

Volume 13, Issue 35

I bet that got your attention. I guess I should note that this is limited to the New England district. That is still a pretty big area and a very large population affected.

The following is a press release from the Corps. The important date is this Wednesday, as in tomorrow. Comments are due then.

Nationwide B

CONCORD, Mass. – The U.S. Army Corps of Engineers, New England District has proposed suspending the existing general permits in each of the six New England states and issuing the New England General Permit (NE GP) to authorize certain activities that require Department of Army permits under Section 404 of the Clean Water Act, Section 10 of the Rivers and Harbors Act of 1899, and Section 103 of the Marine Protection, Research and Sanctuaries Act.

The Corps has extended the public comment period to Aug. 28, 2013. Here is a link to the proposal: http://www.nae.usace.army.mil/Portals/74/docs/regulatory/StateGeneralPermits/NEGP/NEGP-PN.pdf. The original notice was issued on June 13, 2013 with a 45-day comment period. The comment extension is to allow inviduals and groups more time to submit their comments.

The NE GP would authorize activities in waters of the U.S. within the boundaries of and/or off the coasts of the six New England states (Massachusetts, Rhode Island, Connecticut, New Hampshire, Vermont and Maine), including activities occurring within the boundaries of Indian tribal lands that have no more than minimal adverse effects on the aquatic environment.

When GPs were first used in New England in the 1990s, they provided the Corps with significant efficiency, allowing a more streamlined review of minor projects under Section 10 and Section 404. At that time, it made sense to have a separate GP in each state as there were vast differences in state programs and priorities. Over time, however, both the Corps Regulatory program and state wetland programs have evolved. It now makes sense to develop a regional general permit that will continue to maintain a high level of environmental protection while allowing the Corps to streamline processes in New England, reduce regulatory redundancy, ensure consistent compliance with national policy, and alleviate a significant administrative burden for its staff, which currently must reissue each of the six state GPs every five years.

This also would facilitate permit review by partner tribal nations and agencies, be more user-friendly for the regulated public, especially those working in multiple states, and encourage consistency in wetlands and waterway regulation in New England while allowing for flexibility in establishing special conditions, thresholds, and processes that are important to individual states.

The proposed NE GP will not result in significant substantive changes to how activities in waters of the U.S. are regulated in the New England states. The NE GP organizes eligible work into activity-specific categories. This is intended to satisfy the requirements of Section 404(e) of the Clean Water Act, which allows the Corps to issue general permits for activities that are similar in nature and will cause only minimal individual and cumulative adverse environmental effects. Identifying specific activities will allow the Corps to adequately assess cumulative impacts of permitted activities, as well as fully assess impacts on threatened and endangered species.

General Permits are encouraged under the Clean Water Act as a way to streamline state and Federal regulatory programs. The District has had success with streamlining these programs with the use of GPs in New England (in Connecticut since 1990, in Maine since 1983, in Massachusetts since 1993, in New Hampshire since 1992, in Rhode Island since 1997, and in Vermont since 1997).

The public notice with the proposed New England General Permit (NAE 2013-00714) can be reviewed at

http://www.nae.usace.army.mil/Portals/74/docs/regulatory/StateGeneralPermits/NEGP/NEGP-PN.pdf.

Public comments on this proposal should be submitted in writing by Aug. 28, 2013 to the U.S. Army Corps of Engineers, New England District, Regulatory Division (ATTN: Greg Penta), 696 Virginia Road, Concord, MA 01742-2751. Additional information is available from Greg Penta at 978-318-8862 or toll free 800-343-4789 or 800-362-4367 (if calling in Massachusetts) or by email to gregory.r.penta@usace.army.mil. Those who are interested in attending a question and answer session on this topic should contact Greg Penta.